Phase: Concrete footings.
After spending the past 2 weeks dealing with weather, and material supply problems we are back on schedule and have completed the week with a set of rebar cages that by Monday will be ready for inspection by the city. Since Monday most of the work completed has been focused on bending and tieing in the steel that will form the rebar cages for the retaining walls of the iT House.

An unknown that occured on the site this week was the discovery of additional roots in the area where the slab is due to be laid. A Monday morning meeting with the soils engineer will either turn this into a problem or something to ignore.

1 Comments:

Blogger answer-man said...

Hello just stopped by to view your blog and to let all interested know I am offering free plumbing repair information and safety tips for California residents and all others interested. If you are not interested then please excuse us and please disregard this comment.

For Plumbing Press Release and Free Plumbing Repair Information please feel free and stop by and read and take advantage of our blog info or viist **A-Affordableplumbing.Com** Thank you and have a great day.

7:31 PM  

Post a Comment

<< Home