Friday, October 28, 2005

Week 4 Friday Report


Phase: Concrete footings.
After spending the past 2 weeks dealing with weather, and material supply problems we are back on schedule and have completed the week with a set of rebar cages that by Monday will be ready for inspection by the city. Since Monday most of the work completed has been focused on bending and tieing in the steel that will form the rebar cages for the retaining walls of the iT House.

An unknown that occured on the site this week was the discovery of additional roots in the area where the slab is due to be laid. A Monday morning meeting with the soils engineer will either turn this into a problem or something to ignore.

Monday, October 24, 2005

Week 4

Rebar finally shows up on site and layouts are placed and tied.

Monday, October 17, 2005

Week 3

Excavation work is completed, but rain and postponed rebar fabrication slows the project to a temporary halt.

Monday, October 10, 2005

Week 2

Grading work begins on the hillside for the 11' high retaining wall at the back. Also, footing excavation begins for the rebar layouts.

Monday, October 03, 2005

Week 1

Demolition begins on the existing pool patio, jacuzzi, and outdoor BBQ area.