Well, here we are! The end is in sight. Our electricians finished their conduit runs today and we are going for inspection with the City of Villa Park tomorrow morning. It is pretty amazing to see the conduit in electrical conjunction with the plumbing runs, and the duct work (now buried). It’s impressive to think that only a few weeks ago this all seemed like a monstrous task. Now that it’s almost wrapped up, it doesn’t seem that hard.

The final masonry wall is almost complete as well, and by the end of next week we should be ready to pour the slab.














On Monday Alan and I will be on site to lay out the Insul-Tarp and inspect everything prior to the construction of the re-bar grid for the floor slab. After that is complete our mechanical sub will return and layout the radiant flooring. By February 1st we should have a completed slab and be ready to begin the Bosch framing.

1 Comments:

Blogger answer-man said...

Hello just stopped by to view your blog and to let all interested know I am offering free plumbing repair information and safety tips for California residents and all others interested. If you are not interested then please excuse us and please disregard this comment.

For Plumbing Press Release and Free Plumbing Repair Information please feel free and stop by and read and take advantage of our blog info or viist **A-Affordableplumbing.Com** Thank you and have a great day.

7:32 PM  

Post a Comment

<< Home