Week 15: Radiant Flooring

Wow! Things have really moved forward this week. The slab is almost complete and we are looking forward to start erecting the aluminum structural frame. The only thing left to do is pour the concrete on Tuesday and then we'll start setting up the iT Kit pieces.

On Wednesday the mechanical subs moved back onto the job-site and began laying out the radiant flooring. After they outlined the different radiant paths, they attached the radiant tubing to the rebar grid with plastic zip-ties. It was a fascinating process to watch and I was most surprised at the speed at which the work was being completed. By lunch time they were pretty much finished and were working on building the piping for the Munchkin boiler, and radiant flooring controls.

Inspection is scheduled for Monday morning. By Wednesday we'll be posting images of the finished concrete slab.


The Insul-Tarp works in conjunction with the radiant flooring and provides a protective thermal barrier between the radiant flooring in the slab and the ground beneath it. Without insulation, the radiant flooring would loose all of its heat to the ground below.
It took us most of the day to install the Insul-Tarp because we had to work around all of the plumbing, electrical, and HVAC layouts. The whole system is quite elegant and only took a modicum of work to install. The final result was very satisfying and by next week we should have a slab in place.
Back at the office, we’ve been locking in the roofers, finalizing the custom shower design, and planning for all of the finish work that will take place in the coming months. Tomorrow, CALQUAKE, the concrete sub will be laying out the rebar for the slab area. Stay tuned!




